ongoing project status (aponjon) January 2025 Aponjon Block D & E Inception february 2025 Aponjon Block D & E Foundation March 2025 Aponjon Block D & E Tie beam & Ground floor column April 2025 Aponjon Block D & E Ground floor roof casting MAY 2025 Aponjon Block D & E First floor roof casting JUNE 2025 Aponjon Block D & E Second floor column JULY 2025 Aponjon Block D & E Second floor roof casting, Third floor column & Third floor roof rod binding AUGUST 2025 Aponjon Block D & E Third floor roof casting, Fourth floor column & Fourth floor roof rod binding, and Ground floor PCC casting SEPTEMBER 2025 Aponjon Block D & E Fourth floor roof casting, Lift room & Overhead Tank casting, and Brick work in progress.Aponjon Block C Foundation work in progress OCTOBER 2025 Aponjon Block D & E Fourth floor Brick work in progress.Aponjon Block C Foundation work PCC & RCC complete. NOVEMBER 2025 Aponjon Block D & E Brick work, Conceal cutting & Door frame fitting in progress.Aponjon Block C Tie Beam, Column casting complete and preparing for Ground floor roof casting.