ongoing project status (aponjon)

January 2025

Aponjon Block D & E Inception

february 2025

Aponjon Block D & E Foundation

March 2025

Aponjon Block D & E Tie beam & Ground floor column

April 2025

Aponjon Block D & E Ground floor roof casting

MAY 2025

Aponjon Block D & E First floor roof casting

JUNE 2025

Aponjon Block D & E Second floor column

JULY 2025

Aponjon Block D & E Second floor roof casting, Third floor column & Third floor roof rod binding

AUGUST 2025

Aponjon Block D & E Third floor roof casting, Fourth floor column & Fourth floor roof rod binding, and Ground floor PCC casting

SEPTEMBER 2025

Aponjon Block D & E Fourth floor roof casting, Lift room & Overhead Tank casting, and Brick work in progress.

Aponjon Block C Foundation work in progress

OCTOBER 2025

Aponjon Block D & E Fourth floor Brick work in progress.

Aponjon Block C Foundation work PCC & RCC complete.

NOVEMBER 2025

Aponjon Block D & E Brick work, Conceal cutting & Door frame fitting in progress.

Aponjon Block C Tie Beam, Column casting complete and preparing for Ground floor roof casting.